POST-QUALIFICATION
SEC. 34. Objective and Process of Post-qualification. - Post-qualification is the stage where the bidder with the Lowest Calculated Bid, in the case of Goods and Infrastructure Projects, or the Highest Rated Bid, in the case of Consulting Services, undergoes verification and validation whether he has passed all the requirements and conditions as specified in the Bidding Documents.
If the bidder with the Lowest Calculated Bid or Highest Rated Bid passes all the criteria for post-qualification, his Bid shall be considered the "Lowest Calculated Responsive Bid," in the case of Goods and Infrastructure or the "Highest Rated Responsive Bid," in the case of Consulting Services. However, if a bidder fails to meet any of the requirements or conditions, he shall be "post-disqualified" and the BAC shall conduct the post-qualification on the bidder with the second Lowest Calculated Bid or Highest Rated Bid. If the bidder with the second Lowest Calculated Bid or Highest Rated Bid is post-disqualified, the same procedure shall be repeated until the Lowest Calculated Responsive Bid or Highest Rated Responsive Bid is finally determined.
In all cases, the contract shall be awarded only to the bidder with the Lowest Calculated Responsive Bid or Highest Rated Responsive Bid.
SEC. 35. Failure of Bidding. - There shall be a failure of bidding if:
- No bids are received;
- No bid qualifies as the Lowest Calculated Responsive Bid or Highest Rated Responsive Bid; or,
- Whenever the bidder with the highest rated/lowest calculated responsive bid refuses, without justifiable cause to accept the award of contract, as the case may be.
Under any of the above instances, the contract shall be re-advertised and re-bid. The BAC shall observe the same process and set the new periods according to the same rules followed during the first bidding. After the second failed bidding, however, the BAC may resort to negotiated procurement as provided for in Section 53 of this Act.
SEC. 36. Single Calculated/Rated and Responsive Bid Submission. - A single calculated/rated and responsive bid shall be considered for award if it falls under any of the following circumstances:
- If after advertisement, only one prospective bidder submits a Letter of Intent and/or applies for eligibility check, and meets the eligibility requirements or criteria, after which it submits a bid, which is found to be responsive to the bidding requirements;
- If after the advertisement, more than one prospective bider applies for eligibility check, but only one bidder meets the eligibility requirements or criteria, after which it submits a bid which is found to be responsive to the bidding requirements; or
- If after the eligibility check, more than one bidder meets the eligibility requirements, but only one bidder submits a bid, and its bid is found to be responsive to the bidding requirements.
In all instances, the Procuring Entity shall ensure that the ABC reflects the most advantageous prevailing price for the Government.