RULE XIX

Posted: 06 April 2017

CONTRACT PRICES AND WARRANTIES

Section 61. Contract Prices

61.1. For the given scope of work in the contract as awarded, all bid prices shall be considered as fixed prices, and therefore not subject to price adjustment and escalation during contract implementation, except under extraordinary circumstances and upon prior approval of the GPPB, or when a Treaty or International or Executive Agreement expressly allows it pursuant to Section 4 of this IRR.

61.2. In cases where the cost of the awarded contract is affected by any applicable new laws, ordinances, regulations, or other acts of the GoP, promulgated after the date of bid opening, a contract price adjustment shall be made or appropriate relief shall be applied on a no loss-no gain basis.

61.3. Any request for price escalation under extraordinary circumstances shall be submitted by the concerned entity to the National Economic and Development Authority (NEDA) with the endorsement of the Procuring Entity. The burden of proving the occurrence of extraordinary circumstances that will allow for price escalation shall rest with the entity requesting for such escalation. NEDA shall only respond to such request after receiving the proof and the necessary documentation.

For purposes of this Section, "extraordinary circumstances" shall refer to events that may be determined by the NEDA in accordance with the Civil Code of the Philippines, and upon the recommendation of the Procuring Entity concerned.

61.4. All contracts shall be denominated and payable in Philippine currency, and this shall be stated in the Bidding Documents: Provided, however, That subject to the guidelines issued by the GPPB, the Procuring Entity may provide in the Bidding Documents that obligations may be paid in foreign currency; Provided, further, That should the Procuring Entity receive bids denominated in foreign currency, the same shall be converted to Philippine currency based on the exchange rate prevailing on the day of the bid opening for purposes of bid comparison and evaluation.

Section 62. Warranty

62.1. For the procurement of Goods, in order to assure that manufacturing defects shall be corrected by the supplier, a warranty security shall be required from the contract awardee for a minimum period of three (3) months, in the case of Expendable Supplies, or a minimum period of one (1) year, in the case of Non-expendable Supplies, after acceptance by the Procuring Entity of the delivered supplies.

The obligation for the warranty shall be covered by either retention money in an amount equivalent to at least one percent (1%) of every progress payment, or a special bank guarantee equivalent to at least one percent (1%) of the total contract price. The said amounts shall only be released after the lapse of the warranty period or, in the case of Expendable Supplies, after consumption thereof: Provided, however, That the supplies delivered are free from patent and latent defects and all the conditions imposed under the contract have been fully met.

62.2. For the procurement of Infrastructure Projects, the following warranties shall be made:

62.2.1. From the time project construction commenced up to final acceptance, the contractor shall assume full responsibility for the following:

  1. any damage or destruction of the works except those occasioned by force majeure; and
  2. safety, protection, security, and convenience of his personnel, third parties, and the public at large, as well as the works, equipment, installation and the like to be affected by his construction work.

62.2.2. One (1) year from project completion up to final acceptance or the defects liability period.

62.2.2.1. The contractor shall undertake the repair works, at his own expense, of any damage to the infrastructure on account of the use of materials of inferior quality, within ninety (90) days from the time the HoPE has issued an order to undertake repair. In case of failure or refusal to comply with this mandate, the Procuring Entity shall undertake such repair works and shall be entitled to full reimbursement of expenses incurred therein upon demand.

62.2.2.2. The defects liability period shall be covered by the Performance Security of the contractor required in Section 39.1 of this IRR, which shall guarantee that the contractor performs his responsibilities stated in the immediately preceding Section. If the contractor fails to comply with its obligations under Section 62.2.2.1 of this IRR, the Procuring Entity shall forfeit its performance security, subject its property(ies) to attachment or garnishment proceedings, and perpetually disqualify it from participating in any competitive bidding. All payables of the GoP in his favor shall be offset to recover the costs.

62.2.3. From final acceptance of the project up to the period prescribed in Section 62.2.3.2 of this IRR.

62.2.3.1. The following shall be held responsible for "Structural Defects," i.e., major faults/flaws/deficiencies in one or more key structural elements of the project which may lead to structural failure of the completed elements or structure, or "Structural Failures," i.e., where one or more key structural elements in an infrastructure facility fails or collapses, thereby rendering the facility or part thereof incapable of withstanding the design loads, and/or endangering the safety of the users or the general public:

  1. Contractor - Where Structural Defects/Failures arise due to faults attributable to improper construction, use of inferior quality/substandard materials, and any violation of the contract plans and specifications, the contractor shall be held liable;
  2. Consultants - Where Structural Defects/Failures arise due to faulty and/or inadequate design and specifications as well as construction supervision, then the consultant who prepared the design or undertook construction supervision for the project shall be held liable;
  3. Procuring Entity's Representatives / Project Manager / Construction Managers and Supervisors - The project owner's representative(s), project manager, construction manager, and supervisor(s) shall be held liable in cases where the Structural Defects/Failures are due to his/their willful intervention in altering the designs and other specifications; negligence or omission in not approving or acting on proposed changes to noted defects or deficiencies in the design and/or specifications; and the use of substandard construction materials in the project;
  4. Third Parties - Third Parties shall be held liable in cases where Structural Defects/Failures are caused by work undertaken by them such as leaking pipes, diggings or excavations, underground cables and electrical wires, underground tunnel, mining shaft and the like, in which case the applicable warranty to such structure should be levied to third parties for their construction or restoration works.
  5. Users - In cases where Structural Defects/Failures are due to abuse/misuse by the end-user or implementing unit of the constructed facility and/or non-compliance by a user with the technical design limits and/or intended purpose of the same, then the user concerned shall be held liable.

62.2.3.2. The warranty against Structural Defects and Failures shall cover the following periods from final acceptance, except those occasioned by force majeure:

  1. Permanent Structures: Fifteen (15) years

    Buildings of types 4 and 5 as classified under the National Building Code of the Philippines and other structures made of steel, iron, or concrete which comply with relevant structural codes (e.g., DPWH Standard Specifications), such as, but not limited to, steel/concrete bridges, flyovers, aircraft movement areas, ports, dams, tunnels, filtration and treatment plants, sewerage systems, power plants, transmission and communication towers, railway system, and other similar permanent structures;
  2. Semi-Permanent Structures: Five (5) years

    Buildings of types 1, 2, and 3 as classified under the National Building Code of the Philippines, concrete/asphalt roads, concrete river control, drainage, irrigation lined canals, river landing, deep wells, rock causeway, pedestrian overpass, and other similar semi-permanent structures; and
  3. Other Structures: Two (2) years

    Bailey and wooden bridges, shallow wells, spring developments, and other similar structures.

62.2.3.3. To guarantee that the contractor shall perform his responsibilities as prescribed in Section 62.2.3.1(a) of this IRR, it shall be required to post a warranty security in accordance with the following schedule:

Form of Warranty Security Amount of Warranty Security
(Not less than the required percentage
of the Total Contract Price)
a) Cash or Letter of Credit issued by a Universal or Commercial Bank: Provided, however, That the Letter of Credit shall be confirmed or authenticated by a Universal or Commercial Bank, if issued by a foreign bank.

For biddings conducted by LGUs, the Letter of Credit may be issued by other banks certified by the BSP as authorized to issue such financial instrument.
Five percent (5%)
b) Bank guarantee confirmed by a Universal or Commercial Bank. For biddings conducted by LGUs, the bank draft/guarantee may be issued by other banks certified by the BSP as authorized to issue such financial instrument. Ten percent (10%)
c) Surety bond callable upon demand issued by GSIS or a surety or insurance company duly certified by the Insurance Commission as authorized to issue such security. Thirty percent (30%)

62.2.3.4. The warranty security shall be denominated in Philippine Pesos, remain effective for one (1) year from the date of issuance of the Certificate of Final Acceptance by the Procuring Entity, and returned only after the lapse of the said one (1) year period.

62.2.4. In case of Structural Defects/Failure occurring during the applicable warranty period provided in Section 62.2.3.2 hereof, the Procuring Entity shall undertake the necessary restoration or reconstruction works and shall be entitled to full reimbursement by the parties found to be liable for expenses incurred therein upon demand, without prejudice to the filing of appropriate administrative, civil, and/or criminal charges against the responsible persons as well as the forfeiture of warranty securities posted in favor of the Procuring Entity.